Toronto has opened more neighbourhoods to multiplex housing. But permission to build, a permit in hand and a finished home are three different milestones. Understanding the difference makes the conversation about housing delivery more useful.
A Snapshot We Can Check
The City's Multiplex Monitoring Program Final Report, dated May 29, 2025, records the following for May 12, 2023 to November 4, 2024:
- 750 applications
- Building-permit applications for buildings with two to four units.
- 452 permits issued
- Multiplex permits issued during the reporting period.
- 108 permits closed
- 24% of the issued permits had completed construction and inspections.
These are stages of activity, not three groups to add together. They are also a historical snapshot, not a count of homes delivered today. Read the City's figures on page 11 of the report.

A Permit Is a Milestone, Not the Finish Line
For an owner, the useful question is what still stands between the current stage and homes people can move into. A permit moves a project forward. Financing, construction, utility connections and inspections still need to come together.
That is why we approach development as one connected process. Early decisions about the site and building need to hold up when the drawings become a construction schedule, and when the finished homes become someone's everyday life.
Elapsed Time Is Not the Same as Delay
Toronto publishes review standards for complete applications. Its building-permit review streams explain how completeness and applicable-law requirements affect those standards.
Subtracting an application date from an issue date measures elapsed time. It does not tell us how much was avoidable, who was responsible or whether the design changed along the way. A credible delay study would need to make those distinctions before attaching a city-wide number to them.
What We Can Say From Our Own Work
On FAMILY 1, NBRS reached a building permit within four months of closing. We set the site vision and layout early, then pursued an as-of-right design and a preferred variance design in parallel with the consultant team.
That is one project's experience, measured from closing to permit. It is not directly comparable with an application-to-issue interval, and it is not a promise for another property. The useful lesson is the work behind the milestone: clear direction, coordinated decisions and a path forward if the preferred design could not proceed.
Read the FAMILY 1 case study for the decisions behind the building, or our guide to choosing a development team for how that coordination works.
Sources and Update
Updated October 23, 2026. We removed an earlier cumulative-delay estimate because we could not substantiate it. The figures above are attributed to the City's dated report; the FAMILY 1 account comes from NBRS's project experience.