FAMILY 1 is designed as an all-electric, energy-efficient building with five homes in Mimico. Making that possible required more than selecting equipment. The electrical demand had to be modelled, the service capacity checked and an upgrade arranged with Toronto Hydro.
Start with the Building's Electrical Needs
An all-electric design puts heating, cooling, hot water, cooking and other everyday loads into the electrical plan. The design team needs to understand how much power the finished building may draw, and when, before the service request can be properly scoped. The answer depends on the building and equipment; it cannot be assumed from the number of homes alone.
Toronto Hydro's service connection guidance asks owners and contractors to request a new connection or service upgrade when the existing supply will not meet the project's needs. Its process includes review, design and construction steps, with responsibilities on both the applicant's team and the utility.
What It Took at FAMILY 1
For FAMILY 1, arranging the required service upgrade involved about 12 months of load modelling, collaboration, relationship building and advocacy with Toronto Hydro. That coordination ran alongside design and construction.
Our consultants had to translate the all-electric design into a credible load request. The utility had to assess the connection and what work was needed. The contractor's construction sequence then had to account for the service work and inspections. Keeping those people in conversation mattered because a change in equipment or timing could affect another part of the plan.
Why Timing Matters
A finished building that cannot be energized cannot be used as intended. It is a risk to plan around early, because construction debt can continue while move-in is delayed.
For illustration: Three months at $15,000–$25,000 in monthly interest adds $45,000–$75,000 before other carrying costs. Actual exposure depends on borrowing and timing.
The practical lesson is to bring the electrical design and service request into the project schedule early, then keep checking them as the building design develops. It takes coordination among the owner, consultants, utility and contractor. No one party can settle every dependency alone.
You can read more about the homes and decisions behind FAMILY 1.